The 4th Wall..

April 3, 2021 7:12 pm Published by

Why does that make me think of Pink Floyd?

I actually enjoyed building this, as it was not overly difficult, fairly straightforward, and results were easily seen within hours.

It ate through joists like crazy, many 4.8m lengths of them. It was built on the ‘massive’ side of the scale, for a couple of reasons. It saved on cutting down lengths to 4″, and also as well, as it was immediately above a steel girder, could add massive vertical strength to the loft beams.

The first layer to the floor was ‘floated’ on Regupol rubber, a certified weight and vibration absorbing material. Minimal screws through to the floor below to maintain the ‘floating’ aspect, and kept vertical via connections at each end and the ceiling joists (whic are the floor of the loft) All of these were also via Regupol compound as well, keeping the entire wall out of contact with anything else.

Being 6″ thick, and I had no Rockwool that thick to hand, I went with using 4″ on the room side, and 2″ from the warehouse side, worked very well, where I could get to it. Scaffold needs to be in place on warehouse side to finish that part off as well as the last bit of ceiling that I cannot access due to height.

The usual really tricky parts where walls join at each end, and also a top corner to the loft which took a mere 3 days to complete and soundproof.

The usual set of images will give more detail than many words can tell.

IMG_2193
DE4B2C6A-88B1-40EE-AA37-0FDE99311DBA
F1FCADF2-C502-4FD1-B08B-F727D08FF18E
F0ADD390-034C-4CB7-98A1-ADF1F7FB5616
While building the ‘4th’ wall, continuation of lining of the wall to the ouside continued – first framed out, filled with rockwool, then f=genie Clips, Furing Channel and finally sand filled tiles.
99D0FD5E-19DC-4C90-A489-481D89BF82E3
Starting to look like a room..
09FECD78-911E-42EF-B0DD-7B38074DEB95
074E0302-3D59-4535-8827-5C37B2CC354C
Two doorways, plus a pair of double doors to allow large kit to be forklifted into place.
C172C17D-F835-47D8-8E94-FFF447E96D4B
Wiring and additional ‘just in case’ access to more cables to loft.
E6DA8631-7698-494B-BB66-C0EB751892EB
7EDBBD48-FA07-431A-A3A6-0812B0F3103D
This fun little area took 3 days of time to fill and seal correctly, so many odd angles, joints, and such a tough place to work in, 4m off the floor, on a landing area 600mm wide.
803B5953-D4D9-4C01-819E-386BC1F472DC
IMG_2603
E86A2397-97C8-4606-B89A-824A6C60E061
A mere 430Kg right there.
3C7F83A1-D158-4800-B0C0-45E718CDD00D
Control wiring for LED lighting ready to go into place. 25 core Cy cable.
EF9455C3-8F9B-4C8F-89FE-EDD2DBC22144
Cat6A fully shielded ethernet wiring ready for install as well, all 300m of it.
2AF15363-D1D4-4C02-9765-273D28BFABA7
Then of course, the new settee had to arrive and I had to find room for it..
16B79E89-999D-40EE-A634-D65975CC4F2D
91093844-BD32-4D49-AE50-C5EE133DCABC
Along with the new desk (more on this later). Bit of a beast, weighing in at a mere 300Kg.
2D24FB8A-6CFE-4E0A-B590-3431A1BE10E3
IMG_2595
4th wall built, framed, filled with rockwool and covered with first layer of soundproofing.
IMG_2605
Kitchen side begins to be sealed and soundproofed, ready for ‘new’ kitchen.
IMG_2581
Fire doors arrive, ready for finishing, and then putting into place / having frames built to them.
GXAZ1114
First coat.
IMG_2609
Just the thing you need to arrive as you are literally locking up to leave. At least I have something to play with over Easter weekend 2021..
IMG_2610
More sand, adhesive, plasterboard fill.. waiting on 54 Gyproc ‘Plank’ to arrive on holiday Monday.
8E4FDD6A-2F49-4FC4-A099-625DD1256B57
A music room in the making.. This is now up to date – easter 2021.
«
»